GAYA IN Viva Technology
Steam boiler in operation / march 2017
Biomass delivery / september, 21
Commissioning Seminar - Partnership ENGIE-Göteborg Energi / september 2016
On the way to the platform / July 2016
a rainbow for ENGIE / end of APRIL 2016
press SITE'S VISIT / APRIL 2016
installation of the administrative building joineries
december 2015
site delivery and erection of the cheminey / november 2015
Equipment installation and civil works continuation
october 2015
Utilities buildings and gaseifier erection / september 2015
biomass conveyors assembly / AUGUST 2015
steel structures erection / JULY 2015
civil works construction / JUNE 2015
Installation of Prefabricated wall / April 2015
Start of concrete pouring / march 2015
Compaction of the ground / september 2014
Preparation of the ground / june to august 2014
Opening of the construction site / May 5, 2014
Laying of the 1st stone / october 25, 2013